naval station BOQ is not of adequate size to accommodate all the bachelor officer personnel requiring berthing in the Pearl Harbor area. Therefore, we are requesting this project located near the CINCPAC Fleet Headquarters building to house primarily those bachelor officers who work in the CINCPAC Fleet Headquarters area.

MARINE CORPS BASE, CAMP LEJEUNE, N.C.

Senator SYMINGTON. Thank you.

We go to the Marine Corps at Camp Lejeune, N.C., messhall, the second increment.

Our experience has been the Marines seldom ask for anything not essential. And in this instance I notice your justification indicates a serious shortage of messing facilities for enlisted personnel, in the new force troops complex. Just what, General, is the new force troops complex?

General JANNELL. This is a series of four projects that provide barracks, a command headquarters building, and a messhall, and supporting utilities. This complex is the second increment of a previous authorization that was approved in fiscal year 1966, sir. That was for a 1,500man complex as is the second increment.

Senator SYMINGTON. 1,500 men?
General JANNELL. Yes, sir.

MARINE CORPS AIR STATIONS, ORANGE COUNTY, CALIF.

Senator SYMINGTON. Marine Corps Air Stations, Orange County, Calif. You want land acquisitions and easements.

This is quite a substantial amount, $40,379,000 for land acquisition to prevent encroachment upon certain Marine Corps air stations. This to us appears difficult to justify, and we would like a complete explanation as to why it is necessary, and what steps have been taken to secure easements and zoning ordinances, and how much money you expect to spend to accomplish this.

Would you rather file that for the record.

General JANNELL. Yes, sir. We have already provided a point paper to counsel. We can provide it for the record, sir. (The information follows:)

POINT PAPER

PURPOSE

The purpose of this project is to ensure the operational capability of the Marine Corps Air Station (Helicopter) (MCAS(H)), Santa Ana and Marine Corps Air Station (MCAS). El Toro by ensuring compatible development of identified properties in the vicinity of these two stations.

ORIENTATION AND MISSION

These two stations are located on the southeast fringes of the Los Angeles metropolitan area separated by a road distance of approximately seven miles. El Toro is the Marine Corps All-Weather Master-Jet base on the Pacific Coast. It is the headquarters of the Third Marine Aircraft Wing which is in direct support of the ground forces statitoned at Camp Pendleton. MCAS, El Toro supports a high-performance, fixed wing jet operation with eight fighter/attack squadrons, one Composite Reconnaisance Squadron, one Refueler/Transport Squadron, a Marine Reserve Training Detachment. The total is approximately 200 aircraft.

MCAS, El Toro, has a current plant value of $203,650,000, not including land, with an estimated replacement cost at a hypothetical site of $353,242,000 exclusive of land and off-station support. MCAS (H), Santa Ana, is a major helicopter operation, again with all-weather capability, which supports a Tactical Helicopter Group, a Helicopter Training Group, a Marine Reserve Training Detachment and support aircraft totalling 137 heavy and medium helicopters. MCAS (H), Santa Ana has a current plant value of $56,000,000, not including land, with an estimated replacement cost at a hypothetical site of $200,381,000 exclusive of land and off-station support.

Even more so than with the jets, close contact with the ground forces at Camp Pendleton is an essential day-to-day requirement.

ENCROACHMENT PRESSURES

Both stations are feeling the press of encroachment. Housing subdivisions are just across the street from MCAS (H), Santa Ana. At MCAS, El Toro, the properties just outside the fenceline are still in agriculture, but the thrust of events is unmistakable. With this increasing urbanization of Orange County, community pressures, not from private citizens but from various developers, has been a persistent problem requiring the constant attention of the local command.

The first threat was in the early 60's when the Rossmoor Corporation bought the land and commenced planning a senior citizen community directly under the approaches to Runway 34R, the ground controlled approach (GCA) runway. The Marine Corps countered this threat by objections to the required zoning changes. In return for removing its objections to the Rossmoor plan the Marine Corps was granted, through a binding declaration of restrictions, permanent restrictions on the development of a 2000 ft. wide strip, the so-called Rossmoor Greenbelt. Temporary restrictions which expired in 1969 and have been voluntarily extended by Rossmoor, were also obtained on an additional 500 feet on each side of this strip.

Recognizing the threat at Santa Ana, the Marine Corps took action in 1969 to lease 480 acres at Santa Ana on the approach to GCA Runway 24. The estimated cost was $157,000 per year. Authorization for this lease was denied by the Congress with the consensus being that permanent interests should be acquired. These tracts are identified on the attached maps. "A" is the approach to MCAS (H), Santa Ana, and B-3 is the Rossmoor Greenbelt.

To accomplish the Santa Ana acquisition and in recognition of the need to make permanent these temporary restrictions on portions of the Rossmoor Greenbelt, the Marine Corps sought and the Secretary of Defense was given authority in the FY 1971 Military Construction Authorization Act (Sec. 204 and 205, PL 91-511) to acquire these interests through exchange of excess Defense properties.

As of this point in time, no deals have been consumated but the Naval Facilities Engineering Command advises that they are close to an agreement with the Irvine Corporation on Tract "A" at Santa Ana. Unfortunately, no progress is possible on Tract B-3 because of a suit against the Government now pending decision in the U.S. Court of Claims. In this suit, Rossmoor is alleging that the Marine Corps actions constituted a taking and is suing for compensatory damages.

In addition, it has been determined that the exchange authority in the FY 1971 law extends to Tract B-2 where a number of owners are involved. This is still in the appraisal stages with no exchanges yet in prospect.

IRVINE COMPANY AGREEMENT

In 1970 the Irvine Company, the principal land owners in this area, proposed a General Development Plan for its holdings in the vicinity. Again, the Marine Corps had objections. After a series of negotiations during which the interrelated interests of both parties were explored, an agreement and a Memorandum of Understanding were signed with the Irvine Company.

The agreement recognizes Marine Corps interest in certain parcels of land identified as 1 through 7 on the attached maps. Parcels 1, 3, 4 and 5 relate to our interest in restricted development on runway approach and departure routes. Parcel 2 is a site for family housing. Parcels 6 and 7 relate to a proposal to relocate the helicopter heavy lift operations now conducted in parcel 7 to a new

site at parcel 6. The agreement restricts the Irvine Company from any change in current use of these tracts without approval of the Government. However, the Navy Department is committed to initiate action within Fiscal Years 73, 74 and 75 to take acquisition action considered necessary to acquire permanent interests.

PROTECTION PLAN

In view of the terms of this agreement and in recognition of the fact that any reapproachment of the Congress should be on the basis of a complete plan, such a plan was developed.

This plan includes, in addition to tracts which were covered by the FY 1971 Authorization and those included in the Irvine Agreement, two additional parcels, #B-1 and #8. This plan emphasizes the requirement to attain compatible use of the property underlying aircraft approach and departure corridors with safety the primary consideration.

The goal is to provide restricted zones on approach and departure routes. The criteria is, nominally, a 3000 ft. wide strip extending outward from the base of the runway to the point where the typical flight profile attains an altitude of 500 feet above the terrain. This is somewhat extended in the case of the GCA approaches to Runway 34R at MCAS, El Toro, because of the shallow glide slope involved. The interests which are proposed for acquisition in these approach zones are only these required to ensure compatible land use. That is, agriculture. or certain types of recreation not involving large structures or concentration of people. These are the areas where an aircraft is most likely to impact with take-off or landing malfunction.

In addition, there is the matter of noise nuisance or pollution associated with military air operations. The impact of this nuisance can be minimized by acquiring restrictive interests in those areas contained within the composite noise rating-3 (CNR-3) contour.

This is the area subject to noise of an intensity likely to generate complaints. Specifically, this contemplates a requirement in areas outside the runway corridors that any structures within this area must include sound attenuation features. The proposal seeks authority to acquire tangible interests in the property. It is recognized that California State Law and zoning actions afford some measure of protection. However, zoning is subject to the vagaries of local politics. Therefore, authorization to acquire interests is being sought while pursuing the possibility of meeting the objective by zoning and thus obviating the need to exercise the acquisition authority.

AUTHORIZATION REQUEST

The plan calls for authorization of the full plan in FY 1973. This approach avoids piecemealing the problem to the Congress which has already been approached twice regarding these stations. With appropriate authorization, it is intended to vigorously pursue possible exchanges. It is recognized that it is optimistic to expect that all can be obtained by exchange. It is anticipated that appropriation requests would follow in FY 74 and FY 75 for anything which is not obtained by exchange or solid zoning and is still considered essential. This proposal is a major undertaking for the Marine Corps. It is proposed as the only alternative to the prospect of a $500 million requirement to provide replacement facilities at a new site.

TIMING

Timing is a key factor in this proposal. By acting now, negotiations are primarily with one land owner, the Irvine Company, which is under great pressure to release some of its Orange County holdings and should be in a trading mood. Delay would mean dealing with a large number of individual owners and, thereby, reduced hope for property exchange.

[graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]
[graphic][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][ocr errors][subsumed][merged small][ocr errors][merged small]

Senator SYMINGTON. Thank you.

Naval installations air pollution abatement facilities.

Admiral, $25.2 million is a substantial amount for air pollution abatement facilities. I recognize that these projects are necessary in order to comply with existing Federal and State laws. We do notice on page 110, however, that you propose to spend $508,000 for a sanitary land fill at Adak, which is, to say the least, a remote area. Why is this expenditure necessary, and what are we doing now that violates the existing station ordinance?

Admiral ENGER. Commander Groff.

Commander GROFF. Mr. Chairman, all refuse is currently burned in an open dump at Adak. This burning exceeds the 25 pounds per day Federal standard for nonurban areas.