Images de page
PDF
ePub

We have the World Series in the fall, and the excitement generates towards that time. So let us hope that when October 1 arrives that the budget looks good and things are on the move and we can prepare for next spring.

Dr. DRELL. I hope so.

Senator FORD. Thank you, gentlemen. This hearing is adjourned. [Whereupon, at 1:13 p.m., the hearing was adjourned.]

[blocks in formation]

On April 24, 1990, Dr. James F. Decker, Acting Director, Office
of Energy Research, gave testimony before your subcommittee
on Superconducting Super Collider programs.

Enclosed are the

Prior to that hearing, you submitted written questions for
our response to supplement the record.
answers to those questions.

If you have any questions, please have your staff call
Barbara Campbell on 586-8687.

you or your staff.

Sincerely,

She will be happy to assist

Jacquine trox Brows

Jacqueline Knox Brown

Assistant Secretary

Congressional and Intergovernmental Affairs

Enclosure

(177)

PRE-HEARING QUESTIONS AND ANSWERS

FOR THE

APRIL 24, 1990, HEARING

BEFORE THE

SUBCOMMITTEE ON ENERGY RESEARCH AND DEVELOPMENT

COMMITTEE ON ENERGY AND NATURAL RESOURCES

UNITED STATES SENATE

WITNESS: JAMES F. DECKER

ACTING DIRECTOR OF ENERGY RESEARCH

QUESTIONS FROM SENATOR FORD

1. Cost Estimate

Question 1:

The sum of as-spent dollars for the SSC project from FY 1988
through FY 1998 is estimated at $5.9 billion in Department of
Energy budget justifications for FY 1990. DOE has since
indicated that this cost will increase by $1 to $2 billion.
How much is the increase: closer to $1 or closer to $2 billion?

Answer:

The Department is in the process of refining the cost estimates for the SSC project and is conducting a number of independent reviews of the SSC Laboratory's estimate. These reviews will be completed in the June time frame. The Department plans to have validated a cost estimate, along with a baseline design and schedule, in August of this year. A report on this new cost estimate will be provided to the Congress at that time.

In the meantime, it is fair to say that the estimated cost
increase is expected to be closer to the $2 billion number.

[blocks in formation]

Answer:

The details will be provided to the Congress when the final cost estimate for the SSC project, along with the baseline design and schedule have been validated by the Department. This is

expected to occur in August 1990.