Images de page
PDF
ePub

24

(e.g., where piping enters or exits the containment). Even if the shell of the containment is stronger than average, one does not expect a shell rupture to be the first failure point of the containment.

(b). PL&G examined only one containment bypass scenario; however, other bypass scenarios may well be relevant and could produce releases greater than those estimated in the PL&G study.

(c). PL&G has argued that if noble gases are released from the containment after an accident, the containment will hold them long enough to permit decay to levels low enough to warrant a reduction of the EPZ. However, emergency planning as currently conceived assumes that off-site dose-response relationships must be examined without any protective actions. It appears that if noble gases are released without a significant delay, under various realistic worst-case weather scenarios, the acceptable off-site dose levels might well be exceeded at 10 miles.

(d). Assumptions about the radioactive inventory released under high pressure melt ejection scenarios may not be consistent with recent analyses conducted by Sandia National Laboratory on these phenomena.

(e). The report may not adequately consider the prospects that accident recovery actions could cause steam de-inerting by condensation, leading to hydrogen burns or detonation within the containment.

(f). In examining earthquakes as a contributor to radioactive release scenarios, the report may not adequately consider after-shocks while the containment is pressurized, which adds an impulse pressure load.

(g). The report's conclusions on radioactive releases as a consequence of steam generator tube ruptures may not be consistent with recent analyses conducted by Battelle Columbus Laboratory on steam generator tube rupture scenarios.

In summary, it appears that PL&G may have been selective about their assumptions; if one made other, equally reasonable assumptions, the outcome might be much different.

[ocr errors][merged small]

CHRONOLOGY OF KEY MEETINGS/DISCUSSIONS INVOLVING
NRC AND PSNH AND FEMA STAFF RELATIVE TO REDUCED EPZ

July 30, 1985

September 9, 1985

October 10, 1985

October 11, 1985

October 22, 1985

November 26, 1985

-

NRC/PSNH meeting discussion of SSPSA submittal according to NRC this included "the regulatory process including the reassessment of emergency preparedness requirements"

-

NRC/PSNH staff and counsel conference call
Discussion of a possible rulemaking petition and
idea that a 10-mile EPZ is not necessary at
Seabrook based on source term research

-

PSNH counsel, and NRC legal staff discussion
"reduce or eliminate the entire EPZ - Taking
Seabrook PRA applying new source term data

...

-

Discussion that "once technical analysis is done
subject to peer review group if the peer review
group raves, then sometime in Nov. 1985 will come
in with a package"

[ocr errors]

NRC/PSNH staff conference call -- NRC staff notes that feedback about the approach Seabrook was taking on demonstrating the ability to reduce the EPZ appeared to be different from what he understood in an earlier discussion (with PSNH staff)

"(NRC staff) noted that what he explained to (PSNH
staff) in previous discussion was that the approach
Seabrook will need to take is to compare the risk
of Seabrook to the risk of typical reactor (WASH
1400) used as a basis for the regulation. (NRC
staff) suggested Seabrook review NUREG-0396 -- in
the comparison it would be good to compare feature
by feature"

"(NRC staff) said Seabrook should not be developing
the case that Seabrook ..." (incomplete note)
Seabrook coordination meeting with FEMA, NHY, NH
and MA state civil defense staffs - Includes
discussion of impact of the probabilisitic risk
assessment on emergency planning issues

FEMA staff notes that Brookhaven is reviewing the
containment and time-to-failure aspects of the PRA
Discussion of the size of the EPZ and legal
analysis work

Seabrook coordination meeting with FEMA, NHY, NH

72-431 0 - 87 - 2

[merged small][ocr errors][merged small]

December 1985

February 1986

April 1986

July 9, 1986

July 21, 1986

July 25, 1986

July 29, 1986

and MA state civil defense staffs Further
discussion of the PRA and impact on emergency
planning issues

[ocr errors]

"Seabrook Station Risk Management and Emergency Planning Study," Pickard, Lowe, and Garrick

NUREG/CR-4540, "A Review of the Seabrook Station
Probabilistic Safety Assessment: Containment
Failure Modes and Radiological Source Terms,
Brookhaven National Laboratories

[ocr errors]

"Seabrook Station Emergency Planning Sensitivity
Study," Pickard, Lowe, and Garrick

NRC, PSNH, PL&G meeting to discuss PSA program
PSNH submits the Risk Management and Emergency
Planning Study (RMEPS) and the Seabrook Station
Emergency Planning Sensitivity Study to NRC for
review

[ocr errors]

NRC staff meeting "(PSNH staff) says before they go for it give them a reading by October what are the merits of this piece of work does it provide some basis to go forth with exemption"

-

NRC staff notes "What do we [Emphasis added] have to justify to change EPZ? ... need to consider technical and legal" (emphasis in original)

PSNH requests that NRC expedite the technical
review of RMEPS as follows:

"A future submittal, depending on the results of the technical review, may request a change to the emergency response plan process for Seabrook Station. We cannot, at this time, specify what action such a future request may seek, but it is important that we address as soon as possible what options are available to us relative to full power licensing. This is important in light of the apparent strategy of the State of Massachusetts to delay the process." (emphasis added)

July 18 or 29, 1986 NRC staff meeting

-

"(NHY) wants to know if this could serve as a technical argument. If not, he won't file. Point out which technical arguments are good vs. no"

"Seabrook has thrown away containment failure"
"Did they include any real data vs. generic
have to go back and tidy up PRA, but probably not"

[ocr errors]

May

CHRONOLOGY 3

August 5, 1986

August 6, 1986

August 6, 1986

August 11, 1986

August 13, 1986

August 14, 1986

August 27, 1986

-

NRC Staff and PSNH meeting "NRC is beginning an expedited review of the study to assess the technical adequacy of PSNH's analysis to support the study's conclusions."

Brookhaven National Laboratories (BNL) compiles
project description for Review of the Emergency
Planning Sensitivity Study for Seabrook

NRC Staff, BNL, and PSNH onsite walk through
"Objective to reexamine emergency planning basis
wanted enhanced mathodology for site specific
planning -- determine risk impact of different
options"

Internal NRC staff memorandum -- "It is important to decide what direction NRC is going to take on this issue before a detailed technical review can start. A decision chart set up in the form of three questions is attached for your consideration"

NRC staff notes -- PSNH request - "NRC will give

them top priority ... preliminary review in
months normally takes - out of ordinary"

[merged small][merged small][ocr errors][merged small]

"There are so many options get rid of Mass. so they don't have to submit" (emph. added)

-

Meeting at BNL with NRC staff and PSNH NRC staff notes "Do review in short period of time to get positive response or questions needed to get there"

NRC staff - "Unique features of Seabrook containment - Let's try to make it more unique show it's better than average" (emphasis added)

NRC staff and PSNH meeting -- "Review group to (NRC staff), coordinated with the utility, with a list of goals We need to think about what this group can do in 3 months"

...

"What are possibilities

-

-

3 mile EPZ with plume? 1 mile EPZ"

"Agenda (What they could do to show they're
different to get credit)" [original (5']

"Shrinking of planning zone vs. evacuation zone may be able to reduce evacuation zone but not planning zone" (emphasis in original)

...

[merged small][ocr errors]

August 28, 1986

NRC staff memo outlining staff review plan for
Seabrook EPZ Sensitivity Study:

"Goals of review:

1. To provide a technical assessment of the
adequacy of the Seabrook Station Emergency Planning
Sensitivity Study to support its conclusion that
the degree of public protection afforded by a 1
mile emergency planning radius around the Seabrook
Station is equivalent to the degree of protection
that was perceived for a 10 mile emergency planning
radius at the time the 10 mile generic planning
radius was established in NUREG-0396.

2. In the event it is concluded that the Study does not adequately support its conclusion at the 1 mile radius, to determine the radius at which the study can support a conclusion of equivalent protection."

September 26, 1986 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting -- PSNH staff comments: "Step one was for us to write and submit (the safety assessment). We really need to know the conclusion of the NRC as to our results so that we can move forward. We really can't move forward until we know we have some level of agreement."

PSNH: "We started this effort some time ago because we had been getting indications from the State of Massachusetts that in fact what happened last Saturday might happen ... I am not sure whether we would have done it anyway. But given the fact that we have had some difficulty in Massachusetts prompted us to do this in 1985. If nothing else, it certainly lended a sense of urgency to the situation."

ACRS Member: "Can you go ahead by just agreeing with NRC and FEMA that your plans are okay and Massachusetts can sit up there and suck its thumb all it wants?"

PSNH: "... the exercise in New Hampshire will come
possibly after the decision in Long Island. So we
are going to know before we finish with New
Hampshire whether or not that path is really
viable.

"We are trying to learn from everybody. We want to look at every possible alternative and everything we can do so that we increase our range of options in case one option doesn't work."

« PrécédentContinuer »