2. Project No.: 87-R-102

See description, item 8. The estimated costs are preliminary and, in general, indicate the magnitude of each program. These costs include engineering, design and inspection.

1.

CONSTRUCTION PROJECT DATA SHEETS Title and location of project: General plant projects, various locations

10. Details of Cost Estimate

11. Method of Performance

To the extent

Design will be by contractor staff or on the basis of negotiated architect-engineer contracts. basis of competitive bidding. feasible, construction and procurement will be accomplished by firm fixed-price contracts and subcontracts on the

[blocks in formation]

DEPARTMENT OF ENERGY

FY 1987 CONGRESSIONAL BUDGET REQUEST

LEAD TABLE

NUCLEAR PHYSICS

GENERAL SCIENCE AND RESEARCH

(Tabular dollars in thousands. Narrative material in whole dollars.)

[blocks in formation]

Construction....

23,300,

6,702

6,702

33,300

+26,598

$224,2009/

3+59,728

Nuclear Physics..... $181,440/d/ 3164,472d/e/f/5164,472

Staffing Total FTE's

........

(Reference General Science Program Direction
Decision Unit)

Authorization: Section 209, Public Law 95-91.

a/ Includes $3,100,000 Defense Programs support of Clinton P. Anderson Meson Physics Facility (LAMPF) operations.

b/ FY 1985 total reflects a reduction of $835,000 for ADP general reduction.

[ocr errors]

FY 1985 total does not include $1,425,000 transferred to the SBIR program.

d/ Totals reflect a reduction of $1,300,000 in FY 1985, $2,500,000 in FY 1986, and $2,700,000 in FY 1987 for management initiative savings.

e/ $100,000 has been transferred to Assistant Secretary for Environmental Safety and

Health.

f/ Total reduced by $7,328,000 in accordance with P.L. 99-177, the Balanced Budget and Emergency Deficit Control Act of 1985 (Gramm/Rudman/Hollings).

[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

DEPARTMENT OF ENERGY

1987 CONGRESSIONAL BUDGET REQUEST
GENERAL SCIENCE AND RESEARCH
NUCLEAR PHYSICS

1986 Appropriation enacted.. 1986 Gramm-Rudman reduction... 1986 adjusted.....

(In thousands of dollars)

o Provide a cost-of-living increment to maintain a constant level of research activities and facility utilization .....

o Implement Continuous Electron Beam Accelerator Facility (CEBAF) construction and continue R&D which supports the project

o Using recently completed upgrade, conduct AGS heavy ion nuclear research program with 1000 beam hours for research and complete funding for initial complement of detectors

.......

o Provide for accelerator improvement and facility maintenance projects to meet programmatic needs and provide for general purpose equipment to meet laboratory-wide needs of Lawrence Berkeley Laboratory.

o Conduct program operations with overall facility utilization at 55% in FY 1987 ...

$171,800 7,328 $164,472

+ 9,870

+26,180

+ 7,150

+ 1,620

+ 8,230

o Provide for university component of research at 25% of operating expenses and provide for internationally collaborative efforts in solar neutrino research ......

+ 4,058

.......

o Conduct R&D in order to maintain U.S. leadership in accelerator technology

+ 2,620

1987 budget request

$224,200