... facility concerned . " Under NRC regulations now in force , such plans must cover a ten- mile radius around the plant . As you all know , six Massachusetts communities lie within that ten - mile radius . All six of those towns have ...
... facility concerned . " Under NRC regulations now in force , such plans must cover a ten- mile radius around the plant . As you all know , six Massachusetts communities lie within that ten - mile radius . All six of those towns have ...
Page 5
... facility . Decisions regarding a full - power license will not be made for some time ; however , they are complicated by the fact that the Commonwealth of Massachusetts and thirteen local communities have refused to participate in the ...
... facility . Decisions regarding a full - power license will not be made for some time ; however , they are complicated by the fact that the Commonwealth of Massachusetts and thirteen local communities have refused to participate in the ...
Page 7
... facility , at the expense of the citizens of Massachusetts and their rightful participation in the licensing process . To proceed in this fashion would ignore existing emergency planning regulations which are not being met , and would ...
... facility , at the expense of the citizens of Massachusetts and their rightful participation in the licensing process . To proceed in this fashion would ignore existing emergency planning regulations which are not being met , and would ...
Page 15
... facilities and on the adequacy of proposed safety standards . ACRS has been reviewing the study separately from the NRC review , and will provide to NRC in early 1987 an independent recommendation on the merits of the study . At the ...
... facilities and on the adequacy of proposed safety standards . ACRS has been reviewing the study separately from the NRC review , and will provide to NRC in early 1987 an independent recommendation on the merits of the study . At the ...
Page 58
... FACILITIES REQUIRED None . 10. CONFLICT OF INTEREST INFORMATION There are neither significant contractual nor organizational relationships of the Department of Energy , BNL and employees , or expected subcontractors or consultants on ...
... FACILITIES REQUIRED None . 10. CONFLICT OF INTEREST INFORMATION There are neither significant contractual nor organizational relationships of the Department of Energy , BNL and employees , or expected subcontractors or consultants on ...
Autres éditions - Tout afficher
Expressions et termes fréquents
adequate Amesbury applicant assessment ATKINS beach Board of Selectmen Chairman Chernobyl Chernobyl accident Civil Defense communities concerning Conservation and Power containment decision Derrickson Dignan Director discuss documents emergency evacuation Emergency Planning Sensitivity emergency planning zone emergency preparedness emergency response plans Energy Conservation evacuation plan event exercise failure FEMA Governor Dukakis Hampshire Yankee health and safety hearing letter Licensing Board low-power testing MARKEY Massachusetts meeting Memo memorandum November 18 NRC staff NRC's nuclear plant nuclear power plant Nuclear Regulatory Commission Office offsite emergency operating participation planning and preparedness probabilistic risk assessment procedures protective action PSNH public health Public Service questions radiation radioactive Radiological Emergency Response reactor regarding regulations release Representative request RERP risk Seabrook nuclear power Seabrook plant Seabrook Station severe accident Shoreham source term SSPSA Update Stratham Subcommittee on Energy submitted Sununu technical Three Mile Island town utility VOLLMER WINGO