Question 2: Answer: Provide a schedule of projected expenditures for the major components of the project and the project total year-by-year until operation of the facility. The schedule of projected expenditures for the earlier project baselines were presented in the Construction Project Data Sheet for the SSC included in the President's FY 1991 budget request. All of this information is subject to change when the new project baseline is established later this year. I will be pleased to provide that information for the record. (The information follows:) FY 1991 CONGRESSIONAL BUDGET REQUEST SUPERCONDUCTING SUPER COLLIDER a. Engineering, Design, Inspection, and Administration @ approximately 23% of item b.. b. Construction Costs. 1. Conventional Systems. (a) Improvements to Land (site preparations, roads, fencing, and landscaping) (b) General Utilities (electrical, water, communications & waste systems) 90,000 C. (c) Campus Buildings.. (d) Injector Facilities (Structures & underground enclosures). (e) Collider Facilities. (f) Experimental facilities (Structures & underground enclosures) 2. Technical Systems... (a) Injector Systems. (b) Collider Ring Systems (1) Magnets.... (2) Cryogenics. (3) Other systems. Standard Equipment (vehicles and office equipment) d. Contingency @ 21% of above costs. Total Estimated Cost. *Based on March 1986, Conceptual Design Report. $4,300,000 FY 1991 CONGRESSIONAL BUDGET REQUEST FUNDING SCHEDULE OF PROJECT FUNDING AND OTHER RELATED FUNDING REQUIREMENTS (B/A in Millions) FY 88 FY 89 FY 90 FY 91 FY 92 FY 93 FY 94 FY 95 FY 96 FY 97 FY 98b/ Total 0 $209.0 $368.9 $625.0 $673.0 $669.0 $641.0 $641.0 $473.1 $ 0 $4,300.00/ 56.6 59.0 71.3 39.0 23.0 15.0 12.0 3.0 1.7 0 313.6 project costs.. 1.593.6 .... 33.0 97.6 88.7 143.3 134.0 130.0 119.0 196.0 256.8 275.2 120.0 $97.6 $297.7 $512.2 $759.0 $803.0 $788.0 $837.0 $897.8 $748.3 $120.0 $5.893.6 0 80.0 200.0 200.0 300.0 300.0 300.0 300.0 120.0 0 1.800.0 $120.00 $33.0 $97.6 $217.7 $312.2 $559.0 $503.0 $488.0 $537.0 $597.8 $628.3 $120.0 $4.093.6 $33.0 Based on March 1986, Conceptual Design Report. The Department and the SSC Laboratory are in the process of Construction completion 2nd quarter FY 1998. Assumes site provided at no cost to DOE. Total construction cost including anticipated international, state, local Inflation indices used to convert other project costs to then year dollars: FY 1989, 3.1%; FY 1990, 2.6%; FY 1991, Pre-operations shown only through construction project completion. Full cost of initial complement of detectors (including R&D) and central computer. The projection of a total non-Federal contribution to the SSC of $1.8 billion and the year-by-year spread of the Question: Answer: How will the project expenditure year-by-year compare with the estimated budget for the rest of high-energy physics in those years? We would be pleased to provide the outyear projections for the SSC project and the High Energy Physics program associated with the FY 1991 budget request before Congress. These projections are traditionally prepared by the Administration for a five year period only. Therefore, outyear projections beyond those developed for the FY 1991 Congressional budget are not available at this time. It should be noted that these estimates are updated annually as part of the President's annual budget submission to the Congress. I will be pleased to provide that information for the record. (The information follows:) FY 1991 Congressional Budget Request (dollars in thousands) High Energy Physics...... FY 1991 FY 1992 FY 1993 FY 1994 FY 1995 $621,187 $651,100 $674,700 $689,700 $752,100 317,866 570,300 515,600 500,800 550,100 |