... major facilities are located in ten states ; - facilities occupy a total land area about the size of Delaware ; - the average FY 1982 contractor employment will be about 34,500 . Once ( Chart 5 ) As this Chart shows , from the air our ...
... major facilities are located in ten states ; - facilities occupy a total land area about the size of Delaware ; - the average FY 1982 contractor employment will be about 34,500 . Once ( Chart 5 ) As this Chart shows , from the air our ...
Page 47
... Major Gener- al William Hoover , and the Deputy Assistant Secretary for Secu- rity Affairs , Mr. Jim Culpepper , are also with me this morning . I would also like to introduce Major General Dave Einsel , who is the Deputy to the ...
... Major Gener- al William Hoover , and the Deputy Assistant Secretary for Secu- rity Affairs , Mr. Jim Culpepper , are also with me this morning . I would also like to introduce Major General Dave Einsel , who is the Deputy to the ...
Page 109
... major focusing milestones using the Particle Beam Fusion Accelerator - I ( PBFA - I ) and on the design of the next gen- eration facility , PBFA - II . [ Deleted . ] KMSF also has extensive capability in target fabrica- tion and ...
... major focusing milestones using the Particle Beam Fusion Accelerator - I ( PBFA - I ) and on the design of the next gen- eration facility , PBFA - II . [ Deleted . ] KMSF also has extensive capability in target fabrica- tion and ...
Page 111
... major facilities now under construction ? General HOOVER . Defining energy requirements for ignition is the major goal of the ICF program , as it yields a quantum increase in understanding of the ultimate applications of ICF for both ...
... major facilities now under construction ? General HOOVER . Defining energy requirements for ignition is the major goal of the ICF program , as it yields a quantum increase in understanding of the ultimate applications of ICF for both ...
Page 117
... with minimum delays . Design is now underway on all major construction projects . Field offices were authorized to secure on - site architect - engineer contracts to be used on a task - order basis to acomplish engineering 117.
... with minimum delays . Design is now underway on all major construction projects . Field offices were authorized to secure on - site architect - engineer contracts to be used on a task - order basis to acomplish engineering 117.
Autres éditions - Tout afficher
Expressions et termes fréquents
activities additional Admiral MCKEE Agreement alcohol fuels applications Assistant Secretary Atomic Energy Authority BEVILL BOGGS Breeder Reactor BREWER budget request BURGENER Chairman Chart Clinch River completed construction continue contractor core cost DEFENSE PROGRAMS Defense Waste defueling Deleted Department of Energy disposal effort Electric Boat engineering environmental evaluation exemption facilities FAZIO Federal fiscal year 1983 funding going high-level waste impact increase industry Inertial Confinement Fusion inertial fusion information follows laser licensing light water breeder light water reactor megawatt ment million MYERS N Reactor National Laboratory Naval Reactors Navy nuclear materials nuclear waste nuclear weapons operation Pantex percent plans plutonium private sector radioactive radioactive wastes reactor plant reduced research and development ROSER RUDD safeguards Sandia Savannah River schedule Secretary TRIBBLE Shippingport solar spent fuel storage submarine testing tion tritium uranium utility waste management